Adaptation of the 10 kV PIM Overhead Line between Golubac and Brnjica

Power Lines · Golubac · 2022

In order to improve the electricity supply in the area of the town of Golubac and its surroundings, the 10 kV PIM overhead line is being adapted on the section from Golubac to Brnjica, for the investor Elektrodistribucija Srbije, with works starting in 2022. The project works are currently in progress.

The adaptation included the necessary changes to the line, namely the replacement of worn-out electrical and suspension equipment and conductors, clearing of the corridor of vegetation, poles, foundations and earthing systems, the addition of new poles to meet static requirements, as well as the necessary civil and electrical installation works.