35/10 kV “Hipodrom” Preljina Substation
Substations · Čačak, Preljina · 2018 – 2019
Design and construction of 35/10 kV “Hipodrom” Preljina Substation with connected 35 kV cable line. The project was carried out in 2018-2019 under investor ODS EPS Distribucija, Čačak Branch.
The substation comprises facilities and space for transformers. The buildings consist of two parts, a higher one housing the 35 kV (6 cubicles) plant and a lower one housing the 10 kV (10 cubicles) plant, control rooms (DC and AC distribution, remote control and monitoring) and rechargeable battery rooms. The substation has two power transformers, each with 4 MVA power (first phase).
The connection of the substation to the 35 kV network was made by the construction of a new double-circuit 35 kV cable line connecting 35/10 kV Čačak 4 Substation by means of the in/out system with the new 35/10 kV “Hipodrom” Substation. The connection point of the new 35 kV line is the existing conductive cell in 35/10 kV “Čačak 4” Substation Brđani terminal, respectively at the first angle suspension steel tower of the same line, while on the other side, the cable line is introduced into the corresponding 35 kV terminal cells (H2 and H5) in 35/10 kV “Hipodrom” Substation.
The construction of 35/10 kV Hipodrom Substation provides reliable power supply and sufficient amount of energy for the future industrial area, as well as for the entire consumption area in the territory of Preljina – Čačak.
Other References