Static frequency converter, Reversible Hydropower Plant Bajina Bašta

Project description:

The main purpose of the static frequency converter in the reversible hydropower plant Bajina Bašta is to start the aggregate in motor mode, when the power plant works as a pumping plant.

Statički frekventni pretvarač RHE Bajina Bašta

Year of beginning/completion:

2020 – 2022

Location:

HPP-RHPP Bajina Bašta, location: Perućac

Investor:

Javno preduzeće “Elektroprivreda Srbije” Beograd ( Public enterprise “Elektroprivreda Srbije” Belgrade)

Project details

Technical part

The static frequency converter in the RHPP Bajina Bašta has the function of starting the 310 MW motor-generator machine in motor mode, synchronizing it to the 220 kV network.

Delivered equipment, assembled, tested and put into operation: two dry medium-voltage power transformers, SFP cabinet, medium-voltage plant, relay protection, medium-voltage disconnectors, cables and measuring transformers, modification of M/G control cabinet to RHPP and SCADA system.

Social and economic interest

With the help of this project, it is possible for the hydropower plant to work more efficiently because its aggregates will no longer be engaged and switched off for the needs of starting the pumping aggregates in the RHPP, but will be able to work continuously and produce green energy. In this way, around 5 GWh per year will be saved in production, making production more efficient. Also, another important aspect is that with the implementation of this solution, the working and exploitation life of aggregates that are used as power aggregates during synchronous start in flow-through hydropower plants will be extended by eight years, and the need for overhaul will be less. Compared to hydropower plants as we are already familiar with, RHPPs have the role of storing surplus energy, improving energy efficiency in production facilities, because every megawatt of savings, whether in money or energy, brings benefits.

 

Reconstruction of the own consumption system and other activities as part of the HEPS “Zvornik” generator revitalisation – Stage 1: Procurement of a 440 kVA diesel generator

Project description:

Replacement of the existing 280 kVA diesel generator, with a new 440 kVA diesel generator.

Main goal of the own consumption modernisation within the HEPS „Zvornik“ is a provision of a reliable and unobstructed functioning of the production generators, and the entire power plant as well , where it is envisaged that a diesel generator works as a backup power source.

In order for HEPS „Zvornik“ to be modernised, and to enable a connection to the Technical management system, it has been decided to modernise and revitalise the power plant’s electrical and mechanical equipment as well as the buildings. It is particularly taken into consideration that the HEPS „Zvornik“ has been operating for more than 50 years, and that it has reached the end of its lifespan. Therefore, a complete replacement of the existing equipment with a new one is planned, with the application of contemporary solutions related to this equipment, that are necessary for the power plant’s reliable functioning.

Rekonstrukcija sistema sopstvene potrošnje I ostale aktivnosti u sklopu revitalizacije agregata HE Zvornik

Year of beginning/completion:

July 2019 – December 2019

Location:

Mali Zvornik, „Zvornik” Hydroelectric Power Station

Investor:

Public enterprise „Elektroprivreda Srbije“, branch „Drinsko-Limske HE“ Bajina Bašta

Project details

Technical part

A new diesel electric device, with a 440 kVA capacity in Stand-by functioning mode, is intended for an emergency supply of the 0,4 kV 1st priority consumers, who shall be automatically switched on (connected) in case of a basic and backup power supply failure. Generator is connected to the section II of 0,4 kV, 50 Hz main distribution system, on the left bank. A diesel generator has an option of synchronisation, that is, a parallel functioning with a 0,4 kV network.

Diesel generator in Stand-by mode with a nominal power of 440 kVA is a stationary, closed type generator, and represents an emergency power supply source for the priority consumers.

Newly designed condition

For the purposes of backup electric power supply for the priority consumers, a diesel electric generator is designed, type „KOHLER-SDMO“, model: D440, closed type, in a soundproof enclosure. Room intended for a diesel generator facility is made of the solid material waterproof walls. This project also includes the necessary changes aiming to modernise the backup supply.

Geographic position

Hydroelectric Power Station „Zvornik is located on Drina river, in the western part of the Republic of Serbia, in an immediate vicinity of Mali Zvornik. HEPS „Zvornik“, as the furthest downstream location of Drina’s middle course, is a dam toe powerhouse with two mechanical buildings – one on the left, and other on the right bank, that together with a dam are damming the river Drina.

Climate

Climate of Drina’s drainage basin, where HEPS „Zvornik“ is located, is a typical continental climate with changes influenced by the mountains. Practically all the precipitation occurs during the winter months, i.e. from November to April. Frost occurs extraordinarily from November to March. Temperatures go from the lowest point of -30˚C, up to the maximal 40 ˚C.

Social and economic interest

A generator revitalisation increases reliability of the own consumption backup supply system of HEPS “Zvornik”, as well as the degree of safety and stability of power station’s backup supply, which leads to a higher reliability of the power station itself, within the Republic of Serbia’s energy system.

Self-consumption in Đerdap 2 HEPP

Project description:

Delivery and installation of a container diesel generator, with 1250 kVA (1000 kW) power, for 6.3 kV voltage, manufactured by SDMO, and expansion of the self-consumption switchgear in an auxiliary power plant. Diesel generator connection to the power plant’s self-consumption was made by means of a newly designed 6.3 kV three-cubicle generator switchgear manufactured by Schneider Electric (diesel generator connection cubicle, cubicle for diesel generator outgoing feeder connection to the auxiliary power plant and a spare cubicle for connecting any potential load-bank, housed in the diesel generator container which is provided for that particular purpose). The incoming generator connection was made via two new 6.3 kV cubicles in the auxiliary power plant, whose existing self-consumption was expanded by busbar extension.

Start/completion year:

2017 – 2017

Location

“Đerdap 2 HEPP”, Kusjak, near Negotin

Investor:

EPS, Djerdap HEPP Branch, Kladovo

Project details

Technical information

As self-consumption power plants at the main and auxiliary power plants are vital for the operation of the entire power plant in order to prevent accidents, an additional source of independent power supply for self-consumption of “Đerdap 2 HEPP” was installed in the event that a power outage occurs. In case of an accident, the generator can power the entire plant for 72 hours.

Social and economic interest

Safer operation of the power plant, important for the stability of the electric power system and electricity generation.

 

Delivery of a generator circuit breaker, including installation thereof

Project description:

Replacement of the existing generator circuit breaker manufactured by BBC, Switzerland, type: DBV 20 RC 2500 with a new special circuit breaker manufactured by ABB, Switzerland, type: HECS-130R.

Start/completion year:

2018 – 2018

Location:

Đerdap 1 HEPP, Kladovo, Block 2, G4 Generator

Investor:

EPS, Đerdap HEPP Branch, Kladovo

Project details

Technical information

The existing G4 generator circuit breaker in Đerdap 1 HEPP was replaced, including the installation of a cabinet to house the auxiliary equipment of the circuit breaker. Due to the installation of a new generator circuit breaker, adjustments were made to the circuit breaker base and its fitting into the existing rail connection system on both the generator and transformer sides, since the new three-pole group of the installed generator circuit breaker, manufactured by ABB, type: HECS-130R, has different dimensions and structure from the old circuit breaker.

Social and economic interest

The largest hydroelectric power plant in the power system of Serbia.

 

Generator turbine and stator overhaul works

Project description:

Generator turbine and stator overhaul works.

Start/completion year:

2015 – 2015

Location:

“Morava” Thermal Power Plant, Svilajnac

Investor:

EPS, TENT Branch – “Morava” TPP, Svilajnac

Project details

Technical information

Generator stator overhaul works included repairing the hot spots on the stator sheet metals stacks and repairing the looseness of the stator sheet metal stacks. Firstly, the stator outer housing and shields were disassembled, then the generator rotor, hydrogen cooler and all other corresponding components to access the stator itself.

In order to repair hot spots and looseness of stator sheet metal stacks, full stator rewinding, inspection, cleaning and washing of the stator windings were carried out including all necessary tests before and after completion of the work, such as testing the stator winding insulation system parameter, bump test – stator sheet metal stack compaction test, and thermal imaging of stator sheet metal stacks by 1 T induction.

After complete electrical and mechanical assembly of the generator (rotor, bearings, covers, shields, coolers, lubrication and sealing components, flexible connections, brush mounts) and checking the generator gas part and cooling system tightness, as well as all necessary tests, a trial run was performed, respectively generator excitation, generator set first rotation and load synchronisation, including monitoring of generator heating up.

Reports on the executed overhaul works including all measurement and check lists, assessment of the equipment condition prior to and after the overhaul works, as well as recommendations for the next utilisation period were submitted to the user.

Social and economic interest

In addition to regular overhauls at Morava TPP, investment works were also executed for 125 MW generator set overhaul, where Elektromontaža performed stator overhaul.

The overhaul works contributed to the extension of the power plant’s service life, reliability and energy efficiency of the Block, while the operation of the power plant was made compliant with European environmental protection standards.

 

Home generator revitalization

Project description:

Home generator revitalization includes designing, reconstruction of the existing equipment, and delivery and installation of new equipment.

This project covers the following equipment, i.e. the following systems:

  • 750 kVA three-phase synchronous generator (stator and rotor);
  • Pelton turbine, with associated mechanical equipment;
  • System for management, initialization, protection and synchronization of the generator in the network

Start/completion year:

2018 – 2019

Location:

Vlasinske HEPPs Surdulica, Vrla 1 HEPP

Investor:

EPS, Đerdap HEPP Branch, Kladovo

Project details

Technical information

In addition to the main generators in Vrla 1 HEPP, a home generator was installed, intended to be the source of power supply for self-consumption of all 4 power plants. The generators at Vlasinske HEPPs operate at power system loading. The source of the main supply for self-consumption on all Vlasinske Hydroelectric Power Plants is a 10 kV network, via transformers of 10/0.42 kV gear ratios and corresponding rated powers. The 10 kV network connects all 4 power plants and power supply is possible from 3 sources:

  • Main power supply source – via one of two transformers with 35/10 kV gear ratio, 1000 kVA rated power and 110/35 kV transformer from 110 kV network in “Vrla 3” HEPP;
  • Backup power supply source – via home generator in “Vrla 1” HEPP of 0.4 kV voltage, 750 kVA power, and a transformer with 10/0.4 kV gear ratio, 1000 kVA power;
  • Safety power supply source – via 10 kV power line between “Vrla 1” HEPP and Valjevica and 10 kV switchgear in “Vrla 1” HEPP;

The home generator is a horizontal single-jet Pelton turbine that drives a 750 kVA three-phase synchronous generator. It is located in the left part of the powerhouse, viewed upstream, at an elevation of 869.00 meters above sea level.

Social and economic interest

The generator is intended to be the source of power supply for self-consumption of all 4 power plants – Vrla 1, 2, 3 and 4. By correct and reliable handling, the home generator may be utilized in the next 30 years. Fully automatic operation of the generator with remote control was also provided.

 

Hydrogen station in Morava TPP

Project description:

Hydrogen unit – replacement of worn out components. The project envisages adaptation of the existing H2 and CO2 gas distribution unit to ensure safer and more reliable operation.

Start/completion year:

2017 – 2018

Location:

“Morava” Thermal Power Plant, Svilajnac

Investor:

EPS, TENT Branch – “Morava” TPP, Svilajnac

Project details

Technical information

Gaseous hydrogen is used in the technological process of generator cooling. In order to fill the generator with hydrogen and prepare it for operation, it is necessary to purge the generator with carbon dioxide. To ensure safety in this process, it was required to adapt the gas distribution installations consisting of:

• Carbon dioxide unit;
• Hydrogen unit;
• Gas distribution unit;
• Gas analyser panel;
• Hydrogen moisture separator;
• Air moisture separator;
• Expander – carbon dioxide heater.

Social and economic interest

The main objective of the adaptation was to ensure more reliable and safer operation of the gas distribution unit, i.e. to reduce the possibility of fire and explosion in the hydrogen unit by applying safety measures.

With this adaptation, the expansion of the technical gas unit provided two separate rooms, one designed to house hydrogen cylinder bundles and the other to house pressurized liquid carbon dioxide cylinders. A fire wall was constructed between the hydrogen unit and the carbon dioxide unit, with fire-resistance rating of 2 hours without openings, whereby the rooms housing the two units are completely physically separated.

 

Construction of connection for “Košava” WF (two 100 kV connecting power lines and 110 kV “Košava” Switchyard)

Project description:

Construction and adaptation of 2×110 kV power line between Košava Switchyard and Alibunar Substation, 110 kV power line between Košava Switchyard and Vršac 1 Substation, as well as construction of 110 kV Košava Switchyard with 35/110 kV transformation for wind farm.

Start/completion year:

2017 – 2019

Location:

South Banat District – Izbište residential area

Investor:

Prime General Constructions doo Beograd/ MK – Fintel Wind

Project details

Technical information

In terms of functionality, the 110 kV plant is comprised of the part housing the primary air-insulated switchgear and control gear, and a control building housing secondary equipment.

35 kV substation with 35/110 kV transformation and Košava WF complex are connected to 110 kV Košava Switchyard.

110 kV Košava Switchyard is part of the transmission system of Elektromreža Srbije. Pursuant to the EMS requirement, 110 kV Košava Switchyard shall be also capable of operating as an interconnecting plant, i.e. power transmission of one power line through 110 kV Košava Switchyard shall be possible.

The 110 kV plant, including gear, is built outdoors with safety distance for outdoor installation.

Two tubular busbar systems with seven bays are located in the 110 kV plant, and
in the first phase, five bays were equipped as follows:

1 Bay E01 – T01 transformer bay;
2 Bay E02 – line bay to Alibunar Substation;
3 Bay E03 – T02 transformer bay;
4 Bay E06 – coupler bay;
5 Bay E07 – line bay to Vršac 1 Substation.

Room for Bay E04 was left – spare 110 kV line bay, and for Bay E05 – transformer bay, for the third transformer T03, and these bays were not equipped within this project.

Social and economic interest

The construction of wind farms results in generation of electricity from renewable sources, i.e. from wind energy, which makes Serbia strategically positioned as a green energy producer.

Wind power is one of the clean ways to obtain electricity, which is why it is recognized in the world as an important factor for the future of our planet. Wind is a renewable energy source, which means that, unlike fossil fuels, for example, it will not be consumed, and it does not release combustion gases during electricity generation that would increase the greenhouse effect on our planet and thus aggravate global warming.

 

CURRENT PROJECTS

DESULPHURISATION OF
NIKOLA TESLA A TPP

Investor: EPS/
IMP Automatika
Location: Nikola Tesla
Thermal Power Plant, TENT A
Start: 2018

Project details:
Construction of plant for desulphurisation of
flue gases for Nikola Tesla A TPP

REACTIVE
MAINTENANCE OF
BAJINA BAŠTA HEPP

Investor: EPS/ 
Drinsko-Limske HEPPs Branch
Location: Bajina Bašta HEPP
Start: 2018

Project details:
Repairs and maintenance of generators
and associated power equipment
– DL HEPPs Branch

BAJINA BAŠTA
RHEPP
SWITCHGEAR

Investor: EPS/
Drinsko-Limske HEPPs Branch
Location: Bajina Bašta HEPP
Start: 2018

Detalji projekta:
Bajina Bašta RHEPP switchyard
expansion, construction works for 220 kV
plant and reconstruction work for 35 kV plant

RECONSTRUCTION OF
DJURIĆI
PUMPING PLANT

Investor: EPS/
Drinsko-Limske HEPPs Branch
Location: Bajina Bašta HEPP
Start: 2019

Project details:
Procurement and installation of
electrical equipment for reconstruction of
35/6 kV Djurići PP

Download document containing specifications for all projects

Reference list